Having concluded the 12-unit pilot
project at Three Palms Point Condominium Association, I wanted to take
a little time today to discuss where we have been, where we are today,
and where we're going to go with this claim hopefully in the future.
As we all know, Three Palms Point,
in a survey of the building, discovered serious hidden damage to structural
members of this building. Upon finding these damages, my firm was contacted,
and subsequently I was hired to assist them in this claim process. We
then put State Farm on notice of the claim, and State Farm, after conducting
a very lengthy investigation, concluded that, based on the facts that
they had found at Three Palms Point, not only factually as far as the
structure goes, but as well as in the records, that coverage should be
afforded for this collapse/hidden decay claim. State Farm then determined,
unilaterally, that based on their experts, at that time, the knowledge
and information that was available, that this loss would be approximately
$500,000. We, on the other hand, looked at damaged areas, made what we
thought to be a reasonable extrapolation, and presented a claim which
was contained in this booklet for $3.8 million. Unfortunately, both sides
were wrong in this process.
As events have unfolded, as we progressed
forward in this claim, we have discovered that there is asbestos in the
building, we have discovered that there were additional damages above
windows that were not previously contemplated, we've discovered that fasteners
attaching the stucco cladding to the metal studs are impaired and will
be further damaged in removal of the stucco, on the lower sections where
the studs had been rusted. The damages have only gotten worse as we have
progressed in this process. We now know what the loss and damages are
to these 12 units, and based on a reasonable extrapolation, we can say
we feel that this is going to be the end result as far as the cost to
repair this building.
The numbers, as they have been presented
today, based on an audit - I have gone through change orders that have
been submitted, payment requests, notations from the contractor and the
engineer, reflects that those 12 units, total, in our view, after giving
credits where credit is due to State Farm, an amount of $635,607.49. Using
that number and applying an extrapolation based on what we have found
to be damage versus the total lineal feet of the whole building, we've
extrapolated these numbers out for a total repair cost of $13,402,893.
Of course, State Farm has previously paid approximately a half million
dollars, so a credit would have to be given off that amount of money.
Items in the construction of the
original 12 pilot program that were not asked or considered in this included
upgrades for electrical work, new sliding glass doors, new windows and
structural plywood sheathing that was not in place but the Association
has elected to go ahead and put back in their repair process. None of
these items, which would be excluded under law and ordinance coverage
in the policy, are included in these figures.
We at this time feel that the empirical
evidence is in. We now know, based on this pilot program, what the cost
of this project should be in its entirety. As insurance professionals
dealing with property claims, I don't think anyone could disagree that
collapse claims are the most difficult claims to resolve. The difficulty,
of course, is the fact that the granted coverage requires the damage to
be hidden. Clearly, in the Three Palms Point case, the damages were hidden.
State Farm granted coverage for the peril of collapse.
Based on my experience in doing collapse
claims, I have found that the only way that you can resolve the issue
of loss and damages is one, to fix the entire building; you then have
a sum certain amount, or two, you do as we did in this case, a reasonable
extrapolation based on repairs. Call it a template, a pilot program or
what you want, but you've actually repaired units and came up with a figure
based on what has been found to be done. We then applied this extrapolation
to get to the bottom line.
I think that the uncertainty in this
case has been removed. We now know, we all agree, it was done under the
supervision of an engineer, State Farm had the opportunity to inspect
it, the building officials had the opportunity to inspect it, and of course,
the contractor had to perform his job, and all of that has resulted in
these repairs being made at this cost, and using this reasonable extrapolation,
we've arrived at this figure for the loss and damages that occurred at
Three Palms Point.
State Farm and Three Palms Point
throughout this process have worked together. There has been a meeting
of the minds as to units that needed to be done, coverage has been granted,
and I'm very optimistic, based on the evidence that's been presented here,
that we can get this case settled in a timely and equitable manner.
//END//
|